Construction starts on the new Athletics ballpark as crews drill caissons for the foundation and grinding rock
piles on the former Tropicana site on Tuesday, May 13, 2025, in Las Vegas. (L.E. Baskow/Las Vegas Review-Journal)
Work on the Athletics ballpark site is starting to show progress a month after initial grading began on the site of the future $1.75 billion Strip ballpark.
Crews are drilling holes that will be filled with reinforcing steel and concrete and serve as the foundation for the 33,000-fan capacity ballpark, according to Steve Hill, president and CEO of the Las Vegas Convention and Visitors Authority.
“As you can see, they are in the ground,” Hill said, displaying a photo of large caisson drills on the ballpark site. “We have said for over a year, maybe two, that construction would start in April of 2025 — and thanks to the county’s work and all of your (LVCVA) staff, that construction started in April of ’25.”